$3.2M
Annual operating-cost reduction after expansion
CASE STUDY
BEPC supported a multi-phase nitrogen optimization program that reduced annual operating costs, lowered liquid nitrogen trucking dependency, and expanded manufacturing capacity for a medical-device production site.

$3.2M
Annual operating-cost reduction after expansion
90%
Reduction in liquid nitrogen trucking costs
55%
Reduction in nitrogen cost per manufactured unit
The site relied heavily on delivered liquid nitrogen, creating significant transportation costs and limiting support for future production growth. The existing onsite generation system could not meet projected manufacturing demand while maintaining cost targets.
BEPC supported the planning and execution of the nitrogen optimization initiative, coordinating capital planning, engineering, vendors, construction planning, schedule management, commissioning planning, and financial benefit tracking.
The program was sequenced in two phases: first capturing immediate savings through pricing negotiation, then expanding onsite generation with a leased Air Products 40HPN plant and coordinated infrastructure work.
The project transformed the facility's nitrogen supply strategy by shifting from heavy delivered-liquid reliance toward expanded onsite generation. Annual operating cost dropped from $6.6M to $3.4M, monthly trucking cost fell from $451K to $45K, and nitrogen cost per unit improved while annual production volume increased.
Metric
Annual nitrogen operating cost
Baseline
$6.6M/year
Result
$3.4M/year
Change
$3.2M annual reduction
Why it matters
Improved manufacturing cost structure
Metric
Liquid nitrogen trucking cost
Baseline
$451K/month
Result
$45K/month
Change
Approximately 90% reduction
Why it matters
Lower logistics dependency and supply risk
Metric
Nitrogen cost per unit
Baseline
$0.029/unit
Result
$0.013/unit
Change
55% reduction
Why it matters
Better unit economics while volume increased


“The numbers tell the story: nitrogen operating cost went from $6.6M to $3.4M a year and trucking from $451K to $45K a month. BEPC coordinated capital planning, vendors, and commissioning so the savings arrived on the schedule we promised our leadership.”Director of Facilities Engineering - Medical-device manufacturer (name withheld)
Partners & standards
Air ProductsFacilities EngineeringOperationsFinanceProcurementConstruction contractors
Last reviewed: July 2026
Talk to us about a similar facility or capital project. Client details anonymized for confidentiality.

Delivering a $60M biotechnology manufacturing facility
$60M - Manufacturing facility delivered

Hiring event for print shop operators
50% - Interview conversion (10 attendees to 5 interviews)

Commissioning a 162,000 sq ft medical-device cleanroom facility
162,000 sq ft - Facility commissioned