Delivering a $60M biotechnology manufacturing facility

BEPC provided senior project management across site selection, design coordination, permitting, procurement, construction management, schedule control, and turnover for a new biotechnology manufacturing facility.

Industry
Biotechnology / Medical Device
Service
Capital Projects / Construction Management
Project type
Greenfield manufacturing facility construction
Geography
Mexico
Delivering a $60M biotechnology manufacturing facility

$60M

Manufacturing facility delivered

100%

Approved budget and construction schedule maintained

<15years

Projected payback for strategic relocation

The challenge

The client required a new compliant manufacturing facility to support business growth, improve production efficiency, and reduce long-term operating costs while maintaining biotechnology quality and regulatory expectations.

Objectives

  • Build a compliant biotechnology manufacturing facility
  • Increase production capacity
  • Improve operational efficiency
  • Support long-term cost optimization through strategic relocation

BEPC's role

BEPC provided senior project management across the full lifecycle, including site selection, design coordination, permitting, contractor procurement, construction management, schedule control, stakeholder communication, and facility turnover.

Scope & approach

Coordinated land acquisition and site-development activities
Managed multidisciplinary design teams
Oversaw permitting and construction documentation
Led contractor bidding, selection, RFIs, submittals, schedule tracking, and progress meetings

The project was managed through structured capital-project controls, multidisciplinary coordination, and disciplined construction governance using tools such as Microsoft Project and ProCore.

Outcomes

The new manufacturing facility was delivered to expand production capacity, support international operational relocation, maintain budget and schedule discipline, and create long-term cost savings for the client.

Metric

Facility delivery

Baseline

New biotechnology facility required

Result

$60M manufacturing facility delivered

Change

Operational facility turned over

Why it matters

Expanded capacity and supported business growth

Metric

Budget and schedule control

Baseline

Approved capital plan

Result

Budget and construction schedule maintained

Change

Disciplined execution

Why it matters

Protected capital investment and launch timeline

Metric

Strategic relocation economics

Baseline

Long-term operating-cost reduction needed

Result

Projected payback under 15 years

Change

Relocation business case enabled

Why it matters

Supports durable operational cost savings

Visual evidence

Biotechnology manufacturing facility under construction with anonymized exterior
Late-stage construction visual for the greenfield biotechnology manufacturing facility.
Completed biotechnology manufacturing facility interior with anonymized project details
Facility-turnover visual representing construction completion and operational readiness.

Trust & references

From site selection to turnover, BEPC's project leadership kept a $60M build on schedule and on budget while our teams stayed focused on running the business. The facility landed exactly where our capacity plan needed it.

VP of Operations - Global biotechnology and medical-device manufacturer (name withheld)

Partners & standards

Electrical engineeringMechanical engineeringArchitectural engineeringProCoreMicrosoft ProjectBiotechnology regulatory and building-code compliance

Last reviewed: July 2026

HAVE A COMPARABLE CHALLENGE

Talk to us about a similar facility or capital project. Client details anonymized for confidentiality.

Discuss a similar project
View all projects

Next project

Engineering an NPI line conversion from Varipulse to Isopulse

Medical Devices

Read case study
Engineering an NPI line conversion from Varipulse to Isopulse

Download this case study

Choose the format you need and export in one click.