$7.5M
Annual revenue enabled through manufacturing readiness
CASE STUDY
BEPC supported engineering execution for a Varipulse-to-Isopulse NPI program, coordinating line conversion, equipment validation, documentation governance, and production readiness for commercialization.

$7.5M
Annual revenue enabled through manufacturing readiness
$33M
Manufacturing assets validated and prepared for production
$13.66MMXN
Engineering services project value over 10 months
The manufacturing site needed to transition from the Varipulse platform to the next-generation Isopulse platform. The program required complete manufacturing line conversion, equipment validation, documentation readiness, and production transfer while minimizing operational risk and protecting launch timelines.
BEPC provided engineering project management and 11 engineering resources across staff engineering, senior engineering, and validation engineering roles to support the complete NPI process over approximately 10 months.
The team combined cross-functional project governance, equipment validation, documentation control, manufacturing readiness reviews, and production-transfer management to keep the NPI program aligned with commercialization goals.
The project validated and prepared approximately $33M in manufacturing assets, enabled an estimated $7.5M in annual revenue through manufacturing readiness, and supported a 10-month engineering services engagement valued at $13.66M MXN.
Metric
Annual revenue enabled
Baseline
NPI manufacturing readiness required
Result
$7.5M annual revenue enabled
Change
Commercialization supported
Why it matters
Connects engineering readiness to business value
Metric
Capital assets prepared
Baseline
Line conversion and equipment validation required
Result
$33M in manufacturing assets validated
Change
Production assets protected
Why it matters
Supports launch continuity and asset utilization
Metric
Engineering services program
Baseline
10-month NPI execution need
Result
$13.66M MXN project value
Change
Dedicated engineering execution model
Why it matters
Shows scale of BEPC engineering support


“Eleven BEPC engineers carried the Varipulse-to-Isopulse conversion through a ten-month NPI without losing momentum. They readied $33M in manufacturing assets and put us in position to capture the revenue the new platform was built for.”NPI Program Director - MedTech device manufacturer (name withheld)
Partners & standards
NPI engineeringEquipment validationManufacturing readinessDocumentation governanceProduction transfer
Last reviewed: July 2026
Talk to our expert about a similar manufacturing challenge. Client details anonymized for confidentiality.

Transferring sports-medicine manufacturing from Switzerland to Juárez
59 SKUs - Final part numbers launched into production

Launching 30+ assembly lines for cardiovascular medical devices
60+ - Validation resources deployed

Replicating US suture manufacturing across a global supply chain
4 - Countries coordinated